Elie Harbour Fife

Harbour Wall Repointing Works


Client: Elie Harbour Trust
Location: Elie Harbour
Principal Contractor: Menzies
Sector: Marine / Civil Engineering
Project Duration: 6 Weeks

Overview


Repointing works were undertaken to the external face of the harbour wall at Elie Harbour.

Due to restricted access, tidal constraints, and the vertical nature of the structure, the works were delivered using specialist rope access techniques. A dedicated rope access subcontractor carried out the repointing operations externally over the wall face, eliminating the need for large-scale access plant or ground-based scaffolding.

In addition to the repointing works, stone step repairs were carried out within the harbour structure. This included the careful removal, repositioning, and reinstatement of individual stone units weighing up to 1 tonne, requiring controlled lifting operations and precise setting to maintain alignment, stability, and durability within the marine environment.

Working Within a Marine Environment

Due to the location and structure of the harbour wall, traditional access methods were not suitable for the project.

Specialist rope access techniques were utilised to allow safe access to the external face of the harbour wall, eliminating the need for large-scale scaffolding or extensive access plant.

This approach enabled the repointing works to be completed efficiently while minimising disruption to harbour operations and surrounding areas.

Harbour Wall Repairs

The primary scope of works involved repointing sections of the harbour wall to preserve the structure and improve its long-term durability within a coastal environment.

Working in tidal conditions required careful coordination and planning to ensure safe access and consistent quality throughout the project.

The completed repairs helped protect the integrity of the harbour structure while maintaining its operational functionality.

Stone Step Restoration

In addition to the repointing works, stone step repairs were undertaken within the harbour.

The works included the careful removal, repositioning, and reinstatement of individual stone units weighing up to one tonne.

These operations required controlled lifting techniques and precise placement to maintain alignment, stability, and durability within the marine environment.

Project Outcome

The harbour wall repointing works were successfully completed within the six-week programme.

Through careful planning, specialist access methods, and experienced project delivery, Menzies helped preserve an important harbour structure while ensuring safe working practices and minimal disruption throughout the project.

Additional Case Studies


Aerial view of Pettycur Bay Caravan Park in Kinghorn with coastal holiday homes overlooking the Firth of Forth.
Slipway and stone harbour wall at Elie Harbour overlooking the Fife coastline
Menzies site team inspecting works beside an excavator at the Ravenscraig Flats Kirkcaldy project
Industrial process equipment and ductwork installed at the Flexcon Glenrothes facility
Share this project