RNLI Anstruther

Slipway Ramp Removal & Reinstatement


Client: RNLI
Location: RNLI Anstruther Lifeboat Station
Principal Contractor: Menzies
Sector: Marine / Civil Engineering
Project Duration: 8 weeks

Overview


Menzies was appointed by the RNLI to undertake the removal and reinstatement of a temporary slipway ramp at RNLI Anstruther Lifeboat Station. Working within a live marine environment, the project required careful planning, precise sequencing, and strict health and safety controls to maintain operational access throughout the construction programme.

The project involved detailed pre-construction surveys, site clearance, excavation, temporary water management, reinforced concrete construction, and the reinstatement of surrounding infrastructure. Every stage of the works was completed while ensuring the lifeboat station remained operational.

Site Preparation & Marine Construction

Before construction commenced, detailed pre-condition surveys were completed alongside site clearance and the relocation of street furniture and harbour features. Existing concrete elements were carefully broken out before controlled excavation works began.

Due to tidal conditions reaching approximately +2.6m MHWS, temporary water management measures were introduced, including one-tonne sandbags and protective wrapping to safeguard critical phases of construction. These measures allowed work to continue safely within the challenging marine environment.

Slipway Ramp Reinstatement

The new slipway ramp was constructed using reinforced C32/40 early-strength concrete with a geogrid-reinforced sub-base to provide long-term durability.

Works included:

  • Reinforced concrete slipway construction
  • Geogrid-reinforced sub-base installation
  • Integrated movement joints
  • Tamped finish suitable for marine exposure

The completed structure provides a durable, high-performance slipway capable of withstanding the demands of an operational lifeboat station.

Project Delivery

Throughout the eight-week programme, Menzies carefully coordinated the works to minimise disruption while maintaining safe operational access for RNLI personnel.

Following completion, all surrounding surfaces and infrastructure were fully reinstated, leaving the site ready for continued use. The project demonstrates Menzies’ capability to deliver specialist marine civil engineering projects safely, efficiently, and to a high standard in operationally sensitive environments.

Additional Case Studies


Aerial view of Pettycur Bay Caravan Park in Kinghorn with coastal holiday homes overlooking the Firth of Forth.
Slipway and stone harbour wall at Elie Harbour overlooking the Fife coastline
Menzies site team inspecting works beside an excavator at the Ravenscraig Flats Kirkcaldy project
Industrial process equipment and ductwork installed at the Flexcon Glenrothes facility
Share this project