RNLI Anstruther
Slipway Ramp Removal & Reinstatement
Client: RNLI
Location: RNLI Anstruther Lifeboat Station
Principal Contractor: Menzies
Sector: Marine / Civil Engineering
Project Duration: 8 weeks
Overview
Menzies was appointed by the RNLI to undertake the removal and reinstatement of a temporary slipway ramp at RNLI Anstruther Lifeboat Station. Working within a live marine environment, the project required careful planning, precise sequencing, and strict health and safety controls to maintain operational access throughout the construction programme.
The project involved detailed pre-construction surveys, site clearance, excavation, temporary water management, reinforced concrete construction, and the reinstatement of surrounding infrastructure. Every stage of the works was completed while ensuring the lifeboat station remained operational.
Site Preparation & Marine Construction
Before construction commenced, detailed pre-condition surveys were completed alongside site clearance and the relocation of street furniture and harbour features. Existing concrete elements were carefully broken out before controlled excavation works began.
Due to tidal conditions reaching approximately +2.6m MHWS, temporary water management measures were introduced, including one-tonne sandbags and protective wrapping to safeguard critical phases of construction. These measures allowed work to continue safely within the challenging marine environment.
Slipway Ramp Reinstatement
The new slipway ramp was constructed using reinforced C32/40 early-strength concrete with a geogrid-reinforced sub-base to provide long-term durability.
Works included:
- Reinforced concrete slipway construction
- Geogrid-reinforced sub-base installation
- Integrated movement joints
- Tamped finish suitable for marine exposure
- Block paving reinstatement
- Fencing adjustments
- Stairway interface modifications
The completed structure provides a durable, high-performance slipway capable of withstanding the demands of an operational lifeboat station.
Project Delivery
Throughout the eight-week programme, Menzies carefully coordinated the works to minimise disruption while maintaining safe operational access for RNLI personnel.
Following completion, all surrounding surfaces and infrastructure were fully reinstated, leaving the site ready for continued use. The project demonstrates Menzies’ capability to deliver specialist marine civil engineering projects safely, efficiently, and to a high standard in operationally sensitive environments.
Additional Case Studies

Pettycur Bay Holiday Park
Client: Pettycur Holiday Park
Sector:Civil Engineering

Elie Harbour Fife
Client: Elie Harbour Trust
Sector:Marine / Civil Engineering

Northcliff North Queensferry
Client: Private
Sector:Insurance

Ravenscraig Flats Kirkcaldy
Client: FCBS
Sector:Groundworks

RNLI Anstruther
Client: RNLI
Sector:Marine / Civil Engineering

Kinghorn & Lochore Play Areas
Client: Fife Council
Sector: Public Realm/Recreation

ITW Glenrothes
Client: ITW
Sector: Industrial

Glendevon BESS Project
Client: Gransolar Construction
Sector: Renewable

Flexcon Glenrothes
Client: Flexcon
Sector: Groundworks and enabling works

Grange Road, Earlsferry
Client: Mining Remediation Authority
Sector: Frameworks









