Clatchard Court, Newburgh

Gabion Retaining Wall Replacement


Client: Fife Council
Location: Clatchard Court, Newburgh
Sub Contactor: Thomas Menzies Builders Ltd
Sector: Civil Engineering
Project Duration: 21 Weeks

Overview


Thomas Menzies Builders Ltd was engaged to replace a severely deformed retaining wall at Clatchard Court, Newburgh.
The existing 4m-high dressed stone and brick structure was beyond repair and required careful demolition and reconstruction using a gabion basket system.

Due to poor access, the working area was extremely constrained. Services, live public pathways, and proximity to a play park made this a technically demanding project, requiring detailed planning, phased execution, and continuous coordination with Fife Council and other stakeholders.

Scope of Works

  • Vegetation clearance and soft play removal
  • Demolition of the failing masonry retaining wall and brick buttresses
  • Excavation and temporary works for new foundations
  • Installation of reinforced concrete footings with A393 mesh
  • Supply and install of pre-filled gabion baskets with dressed stone facing
  • Granular backfill, kerbing, new pathways, and fencing
  • Reinstatement of play park area and surrounding hard landscaping

Safe Lifting & Access

Access to the work zone was extremely restricted, particularly behind the wall. To overcome this, plant and pre-filled gabion baskets were safely craned onto the working area using pre-arranged lifting operations utilising a 130 tonne mobile crane. All lifting activities were carried out under approved permits and lifting plans, ensuring safety for both workers and the public.

Challenges & Solutions

safety for both workers

Service Avoidance

Underground utilities directly behind the wall required protection throughout all excavation and backfilling operations.

Public Interface

Working adjacent to a live park, safety fencing and signage were maintained daily. Heras panels were installed and relocated as needed to ensure continuous protection of the site boundary.

Access Disputes

A private access issue was encountered early on, requiring careful negotiation to prevent project delays.

Sub-Contractors

  • JML – Gabions
  • R. Lindsey – Surfacing
  • Playtop – Wetpour safety surfacing
  • Archway Metals – Galvanised fencing

Result

The new gabion solution improves slope stability, aesthetics, and safety for residents — demonstrating our capability in delivering complex structural repairs in sensitive public spaces.

Contract was completed 4 weeks ahead of schedule and within Clients’ budget.

Additional Case Studies


Share this project