Clatchard Court, Newburgh
Gabion Retaining Wall Replacement
Client: Fife Council
Location: Clatchard Court, Newburgh
Sub Contactor: Thomas Menzies Builders Ltd
Sector: Civil Engineering
Project Duration: 21 Weeks
Overview
Thomas Menzies Builders Ltd was engaged to replace a severely deformed retaining wall at Clatchard Court, Newburgh.
The existing 4m-high dressed stone and brick structure was beyond repair and required careful demolition and reconstruction using a gabion basket system.
Due to poor access, the working area was extremely constrained. Services, live public pathways, and proximity to a play park made this a technically demanding project, requiring detailed planning, phased execution, and continuous coordination with Fife Council and other stakeholders.
Scope of Works
- Vegetation clearance and soft play removal
- Demolition of the failing masonry retaining wall and brick buttresses
- Excavation and temporary works for new foundations
- Installation of reinforced concrete footings with A393 mesh
- Supply and install of pre-filled gabion baskets with dressed stone facing
- Granular backfill, kerbing, new pathways, and fencing
- Reinstatement of play park area and surrounding hard landscaping
Safe Lifting & Access
Access to the work zone was extremely restricted, particularly behind the wall. To overcome this, plant and pre-filled gabion baskets were safely craned onto the working area using pre-arranged lifting operations utilising a 130 tonne mobile crane. All lifting activities were carried out under approved permits and lifting plans, ensuring safety for both workers and the public.
Challenges & Solutions
safety for both workers
Service Avoidance
Underground utilities directly behind the wall required protection throughout all excavation and backfilling operations.
Public Interface
Working adjacent to a live park, safety fencing and signage were maintained daily. Heras panels were installed and relocated as needed to ensure continuous protection of the site boundary.
Access Disputes
A private access issue was encountered early on, requiring careful negotiation to prevent project delays.
Sub-Contractors
- JML – Gabions
- R. Lindsey – Surfacing
- Playtop – Wetpour safety surfacing
- Archway Metals – Galvanised fencing
Result
The new gabion solution improves slope stability, aesthetics, and safety for residents — demonstrating our capability in delivering complex structural repairs in sensitive public spaces.
Contract was completed 4 weeks ahead of schedule and within Clients’ budget.
Additional Case Studies

Pettycur Bay Holiday Park
Client: Pettycur Holiday Park
Sector:Civil Engineering

Elie Harbour Fife
Client: Elie Harbour Trust
Sector:Marine / Civil Engineering

Northcliff North Queensferry
Client: Private
Sector:Insurance

Ravenscraig Flats Kirkcaldy
Client: FCBS
Sector:Groundworks

RNLI Anstruther
Client: RNLI
Sector:Marine / Civil Engineering

Kinghorn & Lochore Play Areas
Client: Fife Council
Sector: Public Realm/Recreation

ITW Glenrothes
Client: ITW
Sector: Industrial

Glendevon BESS Project
Client: Gransolar Construction
Sector: Renewable

Flexcon Glenrothes
Client: Flexcon
Sector: Groundworks and enabling works

Grange Road, Earlsferry
Client: The Mining Remediation Authority
Sector: Frameworks






