Flexcon Glenrothes
Concrete Slab & Drainage Works
Client: Flexcon
Location: Southfield Industrial Estate, Glenrothes
Principal Designer: Thomas Menzies Builders Ltd
Sector: Groundworks and enabling works
Project Duration: 16 weeks
Overview
Thomas Menzies (Builders) Ltd was appointed as Principal Designer and Contractor for the delivery of a new reinforced concrete foundation slab, drainage infrastructure and associated external works to accommodate Flexcon’s new Regenerative Thermal Oxidizer (RTO) Plant in Glenrothes.
The project was split into three phases: site investigation, detailed design, and construction. We took on full design and build responsibility for the civils package, navigating a complex site with legacy drainage systems, limited space, and critical plant interfaces.
Specialist subcontractors enlisted:
- Ben Hall FRC – Reinforcement Steel
- EuroJet – Drainage Survey
- Technik GS – Piling
Phase 1: Ground Investigation
We began with a comprehensive site investigation including percolation testing, CCTV drainage surveys, and soil sampling. These works were critical to developing an appropriate SUDS strategy for the site, as surface water runoff from the new slab needed to meet strict SEPA treatment requirements.
Phase 2: Design & Coordination
We led the detailed design for the slab and drainage layout. Coordination was key: the slab had to remain level for equipment installation, while still incorporating subtle dishing and drainage channels to manage surface water.
As part of this phase, we consulted on equipment loadings, slab tolerances, windage areas, and future-proofed service ducts.
Phase 3: Construction Delivery
With design frozen, we proceeded to construct the works package, including:
- Service diversions and drainage installations
- Excavation and disposal of inert material
- Capping, sub-base, and reinforced concrete slab (power float finish)
- Reinstatement of paths, fencing and barriers
We also managed site logistics, laydown areas, and welfare setups, coordinating around the client’s operational constraints.
Outcome
The project was led with early-stage collaboration and proactive design management helping Flexcon meet both their technical requirements and programme deadlines. The slab now supports a key element of Flexcon’s low-emissions process infrastructure — with rob ust drainage and future serviceability built in.
Additional Case Studies

Pettycur Bay Holiday Park
Client: Pettycur Holiday Park
Sector:Civil Engineering

Elie Harbour Fife
Client: Elie Harbour Trust
Sector:Marine / Civil Engineering

Northcliff North Queensferry
Client: Private
Sector:Insurance

Ravenscraig Flats Kirkcaldy
Client: FCBS
Sector:Groundworks

RNLI Anstruther
Client: RNLI
Sector:Marine / Civil Engineering

Kinghorn & Lochore Play Areas
Client: Fife Council
Sector: Public Realm/Recreation

ITW Glenrothes
Client: ITW
Sector: Industrial

Glendevon BESS Project
Client: Gransolar Construction
Sector: Renewable

Flexcon Glenrothes
Client: Flexcon
Sector: Groundworks and enabling works

Grange Road, Earlsferry
Client: The Mining Remediation Authority
Sector: Frameworks